An Excess of Construction in Progress Over Partial Billings for Long-Term

Question 34

Multiple Choice

An excess of Construction in Progress over Partial Billings for long-term contracts accounted for on the percentage-of-completion method should be shown as a


A) current asset
B) current liability
C) long-term asset
D) long-term liability

Correct Answer:

verifed

Verified