In Early 2014, the Key West Company Signed a Contract

Question 54

Multiple Choice

In early 2014, the Key West Company signed a contract for construction of an industrial park to be completed in three years. At that time, estimated total costs were $2,250,000, and estimated total revenues were $4,000,000. During 2014, Key West incurred costs of $960,000 and collected $1,100,000. In December 2014, Key West recalculated total costs for the project to be $3,200,000 while estimated total revenues remained unchanged. What amount of profit (loss) should be recognized by Key West for 2014, using the percentage-of-completion method?


A) $266,667 profit
B) $ 55,000 loss
C) $240,000 profit
D) $285,000 loss

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents