The lowest-level work item of any one branch is called
A) a work package.
B) a deliverable.
C) an assignment.
D) a product.
Correct Answer:
Verified
Q82: Once the project scope document has been
Q83: The work packages are at a level
Q84: The _ at a level of a
Q85: In order to prevent poor quality and
Q86: The WBS is _ of deliverables or
Q88: _ is a structured approach for organizing
Q89: The project scope document defines _ in
Q90: To help assure quality, the project quality
Q91: A _ emphasizes who is responsible for
Q92: The _ all of the lowest-level work