The states the specific deliverable that is expected to be completed from the work activities associated with each lowest level-work package.
A) WBS in an indentured list format
B) WBS in a hierarchical graphic chart format
C) responsibility assignment matrix
D) network diagram
Correct Answer:
Verified
Q81: The work packages are at a level
Q82: Once the project scope document has been
Q83: The work packages are at a level
Q85: In order to prevent poor quality and
Q87: The lowest-level work item of any one
Q88: _ is a structured approach for organizing
Q89: The project scope document defines _ in
Q93: The WBS should be decomposed to a
Q98: Quality standards that will be used should
Q99: It is important to plan for _