Having the person who will be responsible for performing a specific activity estimate the duration for that activity ____ from that person and ____ that may be introduced by having one person estimate the durations for all of the activities.
A) takes more effort, creates a problem
B) gives the status of the project, sets best practices
C) generates a commitment , avoids any bias
D) elevates the placement perception, creates errors
Correct Answer:
Verified
Q21: When the customer requests a change, the
Q22: If an organization or subcontractor has performed
Q23: Changes might be initiated by the customer
Q24: A change in the estimated duration of
Q25: The amount of slack should determine the
Q27: The estimated types and quantities of resources
Q28: It is necessary to monitor the progress
Q29: An updated project schedule can be generated
Q30: Changes requested early in the project always
Q31: In many cases, especially for smaller projects,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents