Latest start time is calculated by
A) subtracting the activity's estimated duration from the activity's succeeding activity's latest finish time: LS = LF succeeding activity - Estimated Duration.
B) adding the activity's estimated duration to the predecessor of the activity's latest start time: LS = LS predecessor + Estimated Duration.
C) subtracting the activity's estimated duration from the activity's latest finish time: LS = LF - Estimated Duration.
D) adding the activity's estimated duration to the activity's latest finish time: LS = LF + Estimated Duration.
Correct Answer:
Verified
Q43: Calculate the latest finish for Task D
Q44: The ES and EF times are determined
Q45: Calculate the earliest finish for Task D
Q46: The earliest start time for a specific
Q47: Latest finish time (LF)is the latest time
Q49: Total Slack is sometimes called
A) drift.
B) ride.
C)
Q50: Calculate the earliest start for Task D
Q51: Calculate the latest start for Task D
Q52: Latest start time (LS)is the latest time
Q53: With projects for which there is a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents