The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.How much slack does the project have?
A) Negative 5 days slack.
B) Positive 5 days slack.
C) Positive 17 days slack.
D) Positive 3 days slack.
Correct Answer:
Verified
Q58: Calculate the latest start for Task B
Q59: Earliest start time (ES)is the earliest time
Q60: Calculate the earliest finish for Task B
Q61: Free slack is calculated by finding the
Q62: Analyzing the schedule to determine which areas
Q64: Schedule control involves four steps.Place these steps
Q65: With respect to the project schedule, changes
Q66: As the project progresses, the actual finish
Q67: If the planned corrective actions do not
Q68: The estimated duration for each activity is
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents