The statement, "Network diagrams illustrate the technical constraints among activities," means the activities are constrained because
A) each of the activities are independent from the other activities.
B) one activity cannot be started until the predecessors are finished.
C) the activities use different resources to be completed.
D) some activities use the same resources that may not be available.
Correct Answer:
Verified
Q4: A resource requirements plan illustrates
A) who is
Q5: The start of noncritical activities are delayed
Q6: At a minimum, network diagrams illustrate the
Q7: _ assist with the complexity of generating
Q8: Resource utilization charts based on each activity's
Q10: In resource-limited scheduling, the lower priority activities
Q11: Why are activities drawn in a serial
Q12: Resource utilization charts based on each activity's
Q13: Resource leveling, or smoothing, is a method
Q14: When several activities need the same limited
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents