Why are activities drawn in a serial relationship in a network diagram?
A) The activities use different resources.
B) The activities are independent of each other.
C) From a technical standpoint, the activities must be performed in that sequence.
D) The order of completion doesn't matter.
Correct Answer:
Verified
Q6: At a minimum, network diagrams illustrate the
Q7: _ assist with the complexity of generating
Q8: Resource utilization charts based on each activity's
Q9: The statement, "Network diagrams illustrate the technical
Q10: In resource-limited scheduling, the lower priority activities
Q12: Resource utilization charts based on each activity's
Q13: Resource leveling, or smoothing, is a method
Q14: When several activities need the same limited
Q15: Resource-limited scheduling will not extend the project
Q16: Resource leveling, or smoothing, levels the resources
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents