Select which of the following does not describe how the sequence of activities can be drawn to reflect the availability of a limited quantity of resources.
A) The activities using the limited resources are shown in a ladder relationship as they are available.
B) The activities using the limited resources are shown in a loop relationship as they are available.
C) The activities requiring the limited resource are assigned at different times.
D) If there is no technical constraint for the activities, the activities could be arranged serially by the availability of the resources.
Correct Answer:
Verified
Q12: Resource utilization charts based on each activity's
Q13: Resource leveling, or smoothing, is a method
Q14: When several activities need the same limited
Q15: Resource-limited scheduling will not extend the project
Q16: Resource leveling, or smoothing, levels the resources
Q18: This example has level resources of three
Q19: Which of following would allow for level
Q20: Activities can be delayed only to the
Q21: Resource requirements graphs based on an as-late-as-possible
Q22: Activities drawn in a serial relationship illustrate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents