Resource utilization charts based on each activity's earliest start time are said to be based
A) on availability times.
B) an as-late-as-possible (ALAP) schedule.
C) on an as-soon-as-possible (ASAP) schedule.
D) on a limited schedule plan.
Correct Answer: