The Start of Noncritical Activities Are Delayed Beyond Their Earliest

Question 5

Multiple Choice

The start of noncritical activities are delayed beyond their earliest start times (but not beyond their latest start times) in order to


A) schedule with a technical constraint.
B) schedule with a resource constraint.
C) level the costs of the project.
D) maintain a uniform level of required resources.

Correct Answer: