The project cost estimate is allocated to
A) the various work packages in the project work breakdown structure.
B) the resources in the project.
C) the committed costs in the project.
D) the stakeholders.
Correct Answer:
Verified
Q26: Contingency costs in the project costs estimate,
Q27: The _ for the entire project or
Q28: To keep track of _, it's necessary
Q29: Once a total budgeted cost has been
Q30: It is important to use the _
Q32: When the budgets for all the work
Q33: The _ is the amount that was
Q34: Often, the sum of the initial estimated
Q35: At the beginning of the project, it
Q36: There are two approaches to establishing the