Often, the sum of the initial estimated costs is greater than the amount of funds budgeted by the sponsor.What should be done to arrive at an acceptable budget amount?
A) Cut the cost of the highest priced activity in half until the budget is reached.
B) Trade experienced and efficient resources for less experienced and less efficient resources.
C) Revise the budget expecting that several iterations may need to be made to reduce the costs.
D) Extend the scope of the project.
Correct Answer:
Verified
Q29: Once a total budgeted cost has been
Q30: It is important to use the _
Q31: The project cost estimate is allocated to
A)
Q32: When the budgets for all the work
Q33: The _ is the amount that was
Q35: At the beginning of the project, it
Q36: There are two approaches to establishing the
Q37: Committed costs need to be treated in
Q38: It may be easier to estimate the
Q39: Facilities costs in the project costs estimate
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents