Large Projects Would Have Charge Codes for the Work Package

Question 24

Multiple Choice

Large projects would have charge codes for the work package numbers to


A) have a place for other projects to charge expenses.
B) determine how the actual costs compare to the planned costs.
C) have resources be able to determine what tasks they should complete.
D) allow for cutting of the budget for the activities if need to cut the budget.