The ____ is the amount that was budgeted to accomplish the work that was schedule to be performed up to that point in time.
A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative actual cost (CAC)
D) cumulative earned value (CEV)
Correct Answer:
Verified
Q43: The _ is the sum of the
Q44: If the cumulative earned value is $10
Q45: Consider a project that involves painting five
Q46: Calculate the forecasted cost at completion if
Q47: Costs are _ when an item is
Q49: It's important that the person estimating the
Q50: Calculate the cost variance if the cumulative
Q51: A third method for determining the forecasted
Q52: Another indicator of cost performance is cost
Q53: The _ is the amount that was