In ____, All the Resources Needed to Accomplish Each Project

Question 39

Multiple Choice

In ____, all the resources needed to accomplish each project are assigned full-time to work on that project.


A) an autonomous project organizational structure
B) a functional organizational structure
C) a matrix organizational structure
D) a project management office