On Larger, More Complex Projects, _____

Question 35

Multiple Choice

On larger, more complex projects, _____.


A) the contract development is typically managed through the parent company
B) the contract development is managed by a part-time person assigned to the project
C) the contract execution is typically managed through the parent company
D) the procurement team can consist of work teams within the procurement function with special expertise in contracting
E) the procurement team cannot consist of work teams

Correct Answer: