When the quantity of materials purchased is not equal to the quantity of material used, most companies base the calculation of the material quantity variance on the:
A) quantity of direct materials purchased.
B) quantity of direct materials spoiled.
C) quantity of direct materials that should have been used in achieving actual production.
D) quantity of direct materials actually used.
E) none of the other answers are correct.
Correct Answer:
Verified
Q3: Variances are computed by taking the difference
Q6: Which of the following choices correctly indicates
Q7: Which of the following choices correctly notes
Q12: Which of the following is a predetermined
Q18: The Purchasing Department would normally begin an
Q22: Consider the following statements:
I. Behavioral scientists find
Q29: Consider the following statements:
I. The standard cost
Q34: Which of the following individuals is least
Q38: Most companies base the calculation of the
Q40: Which of the following are methods for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents