During the most recent month at Coggan Corporation,queue time was 5.3 days,inspection time was 0.5 day,process time was 1.9 days,wait time was 4.5 days,and move time was 0.5 day.
Required:
a.Compute the throughput time.
b.Compute the manufacturing cycle efficiency (MCE).
c.What percentage of the production time is spent in non-value-added activities?
d.Compute the delivery cycle time.
Correct Answer:
Verified
= Process time + Inspe...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q83: Saffer Corporation keeps careful track of the
Q84: Heavey Fabrication is a division of a
Q85: Waltner Corporation's management reports that its average
Q86: Jaster Corporation's management keeps track of the
Q87: Financial data for Windsor,Inc.for last year appear
Q88: Ferris Wares is a division of a
Q89: Madrazo Corporation uses residual income to evaluate
Q90: Iles Industries is a division of a
Q91: Durkee Corporation keeps careful track of the
Q93: The Casket Division of Rosencranz Corporation had
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents