Question 5

Multiple Choice

Steele Company uses a predetermined overhead rate based on machine hours to apply manufacturing overhead to jobs. Steele Company has provided the following estimated costs for next year.  Direct materials. £20,000 Direct Labour 60,000 Sales commissions 80,000Salary of production supenisor 40,000 Indirect materials 8,000 Advertising expense 16,000 Rent on factory equipment 20,000\begin{array}{lrr} \text { Direct materials. } &£ 20,000\\ \text { Direct Labour } &60,000\\ \text { Sales commissions } &80,000\\ \text {Salary of production supenisor } &40,000\\ \text { Indirect materials } &8,000\\ \text { Advertising expense } &16,000\\ \text { Rent on factory equipment } &20,000\end{array}

Steele estimates that 10,000 direct Labour hours and 16,000 machine hours will be worked during the year. The predetermined overhead rate per hour will be:


A) £4.25.
B) £8.00.
C) £9.00.
D) £10.25.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents