Maintenance costs at a Whetsel Corporation factory are listed below:
Management believes that maintenance cost is a mixed cost that depends on machine-hours.Use the high-low method to estimate the variable and fixed components of this cost.Compute the variable component first and round off to the nearest whole cent.Compute the fixed component second and round off to the nearest whole dollar.These estimates would be closest to:
A) $8.86 per machine-hour;$20,577 per month
B) $0.11 per machine-hour;$48,192 per month
C) $15.48 per machine-hour;$48,103 per month
D) $8.81 per machine-hour;$20,718 per month
Correct Answer:
Verified
Q83: Supply costs at Chobot Corporation's chain of
Q84: Baker Corporation has provided the following production
Q85: Harris Corporation is a wholesaler that sells
Q85: Gabat Inc. is a merchandising company. Last
Q86: The following data pertains to activity and
Q88: Electrical costs at one of Kantola Corporation's
Q89: Anderson Corporation has provided the following production
Q90: The following data pertains to activity and
Q91: Oaklis Company has provided the following data
Q92: The following cost data pertain to the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents