Solved

The Ferris Company Applies Manufacturing Overhead Costs to Products on the Basis

Question 43

Multiple Choice

The Ferris Company applies manufacturing overhead costs to products on the basis of standard direct labor-hours. The standard cost card shows that 3 direct labor-hours are required per unit of product. For August, the company budgeted to work 90,000 direct labor-hours and to incur the following total manufacturing overhead costs: The Ferris Company applies manufacturing overhead costs to products on the basis of standard direct labor-hours. The standard cost card shows that 3 direct labor-hours are required per unit of product. For August, the company budgeted to work 90,000 direct labor-hours and to incur the following total manufacturing overhead costs:   During August, the company completed 28,000 units of product, worked 86,000 direct labor-hours, and incurred the following total manufacturing overhead costs:   The denominator activity in the predetermined overhead rate is 90,000 direct labor-hours. -For August, the variable overhead efficiency variance is: A)  $1,800 F B)  $0 C)  $2,200 U D)  $2,200 F During August, the company completed 28,000 units of product, worked 86,000 direct labor-hours, and incurred the following total manufacturing overhead costs: The Ferris Company applies manufacturing overhead costs to products on the basis of standard direct labor-hours. The standard cost card shows that 3 direct labor-hours are required per unit of product. For August, the company budgeted to work 90,000 direct labor-hours and to incur the following total manufacturing overhead costs:   During August, the company completed 28,000 units of product, worked 86,000 direct labor-hours, and incurred the following total manufacturing overhead costs:   The denominator activity in the predetermined overhead rate is 90,000 direct labor-hours. -For August, the variable overhead efficiency variance is: A)  $1,800 F B)  $0 C)  $2,200 U D)  $2,200 F The denominator activity in the predetermined overhead rate is 90,000 direct labor-hours.
-For August, the variable overhead efficiency variance is:


A) $1,800 F
B) $0
C) $2,200 U
D) $2,200 F

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents