In 2014, Brunswick Plumbing Supplies planned the following:
Factory overhead costs $180 000
Direct labour costs (15 000 hours at $8.00 per hour) $120 000
Machine Hours 48 000
Direct material costs $108 000
The predetermined overhead rate is based on direct labour hours and planned production during 2014 is 12 000 units. The estimated cost per unit produced is:
A) $24.00.
B) $44.00.
C) $34.00.
D) $26.00.
Correct Answer:
Verified