Solved

John,a Civil Engineer,pays the Heavy Equipment Provider an Agreed-Upon Hourly

Question 64

Multiple Choice

John,a civil engineer,pays the heavy equipment provider an agreed-upon hourly rate and unit price for the various materials to be used.In the context of contract categories,this scenario is an example of a:


A) cost-plus-fee contract.
B) cost-plus-percentage contract.
C) fixed-price contract.
D) time and material contract.

Correct Answer:

verifed