Solved

For a Construction Firm Using the Completed-Contract Method,if Costs Exceed

Question 28

Multiple Choice

For a construction firm using the completed-contract method,if costs exceed billings on some contracts by $1,000,000 and billings exceed costs by $800,000 on others,the contracts should ordinarily be reported as a


A) current asset of $200,000.
B) current liability of $200,000.
C) current asset of $1,000,000 less a contra-current asset of $800,000.
D) current asset of $1,000,000 and a current liability of $800,000.