Which of the following are advantages of computer simulation over analytical methods like PERT/CPM for predicting the probability that a project will complete by a deadline?
I. It does not need to make as many simplifying assumptions.
II. It is more flexible about which probability distributions can be used.
III. It provides a solution more quickly.
A) I only
B) II only
C) III only
D) I, II, and III
E) I and II only
Correct Answer:
Verified
Q39: The PERT method for project management assumes
Q40: The normal distribution is a good choice
Q41: Which of the following charts shows a
Q42: Which of the following distributions describes the
Q43: Which of the following is not a
Q45: Which of the following distributions is widely
Q46: The cell that represents the output of
Q47: Which of the following is not a
Q48: Which of the following is not one
Q49: Which of the following distributions describes the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents