Projects with a zero or positive net present value (NPV) are accepted using the net present value method. Why is this so?
A) Because a non-negative NPV ensures the company will be profitable.
B) Because the company will have the relevant cash flow to pay its debts as, and when, they fall due.
C) Because the return is at least equal to the cost of capital.
D) Because a non-negative NPV ensures the company will be profitable AND because the company will have the relevant cash flow to pay its debts as, and when, they fall due.
Correct Answer:
Verified
Q55: Which of the following statements is incorrect?
A)
Q56: Which of the following capital investment decision
Q57: Assuming interest rates average 6 per cent,
Q58: Which of the following statements is true?
A)
Q59: Which of the following relates to an
Q61: A machine will cost $28 000. It
Q62: The manager of Malan Pty Ltd wants
Q63: Wakefield Company management evaluates future projects based
Q64: Charlotte Computer Services is considering purchasing equipment
Q65: Abco Pty Ltd is considering the purchase
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents