The three inputs for every MRP parts explosion are:
A) Inventory,master schedule,and bill of materials
B) Forecast,inventory,and bill of materials
C) Capacity,master schedule,and inventory
D) Forecast,bill of materials,and master schedule
Correct Answer:
Verified
Q1: A requirements-based system derives orders from:
A)Customer requests
B)Forecast
C)Bill
Q4: Which of the following most closely describes
Q5: The parts explosion results in the following
Q8: A replenishment-based system derives orders from:
A)Capacity available
B)Forecast
Q10: In MRP "scheduled receipts" are:
A)Identical to "planned
Q11: A Type II MRP system:
A)Only launches orders
B)Has
Q12: Which of the following is true about
Q13: Successful MRP implementation requires:
A)Management support,parts explosion,and adequate
Q14: Cycle counting:
A)Is counting a fraction of inventory
Q14: An inflated master production schedule:
A)Is needed to
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents