Multiple critical paths can exist under CPM because:
A) There is more than one way to complete the project
B) Different network paths exist,each with the same total time
C) Great flexibility of activity sequences is available
D) None of the above
Correct Answer:
Verified
Q3: A forward pass of the above network
Q4: The advantage(s)of the network method over the
Q5: CPM network scheduling assumes a second order
Q6: Which of the following statements about CPM
Q7: A network-based project scheduling method that requires
Q8: The project management concept that can be
Q10: Controlling a project does NOT entail:
A)Monitoring costs,time,and
Q11: "Slack" refers to the difference between:
A)Late and
Q13: An assumption of PERT is:
A)Activity times are
Q32: A forward pass is required while computing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents