Critical Ratio is:
A) The ratio between processing time and the idle time of the process
B) The ratio between remaining time until due date and the remaining processing time
C) The ratio between remaining processing time and the remaining time until due date
D) Greater than one if the job is behind schedule
E) Two of the above
Correct Answer:
Verified
Q14: Which of the following questions is NOT
Q15: The SPT rule does a better job
Q16: Aggregate planning and scheduling differ in that:
A)The
Q17: Scheduling often deals with which three conflicting
Q19: Finite capacity scheduling assumes which of the
Q19: Scheduling systems need NOT answer which of
Q20: According to Goldratt:
A)An hour lost at the
Q21: First come,first served is widely used in
Q26: Optimal sequencing rules have found widespread use
Q42: What are the steps that could be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents