On a CPM/PERT network if activity 3 with an activity time of 1,ES=3 and LS=4,is followed by activity 4 with an activity time of 3 and LF=8,and activity 5 with an activity time of 1 and LF=7,the LS for activity 3 is
A) 3
B) 4
C) 5
D) 6
Correct Answer:
Verified