Based on the Following Figures,the Predetermined Manufacturing Overhead Rate Is

Question 83

True/False

Based on the following figures,the predetermined manufacturing overhead rate is $20 per machine hour.Budgeted manufacturing overheads $240 000
Actual manufacturing overheads $250 000
Budgeted machine hours 10 000
Actual machine hours 12 000

Correct Answer: