_______________ relationship is the sequential relationship of project activities to each other.
A) Precedence
B) Scheduling
C) Slack
D) Prior
Correct Answer:
Verified
Q51: Which of the following is not used
Q52: A bar graph displaying when activities are
Q53: In project management the term slack refers
Q54: The longest path through a project network
Q55: For an activity-on-node (AON)network,
A)arrows represent activities and
Q57: One disadvantage of Gantt charts,especially for large
Q58: Which of the following is not one
Q59: Which of the following is the universal
Q60: _ is the process of making sure
Q61: A project consists of the following activities: