Five jobs are waiting for processing through two work centres.Their processing time (in minutes) at each work centre is contained in the table below.Each job requires work centre Alpha before work centre Beta.According to Johnson's rule,what is the optimum sequence of jobs and the minimum time for completion of all jobs?
A) V-T-S-U-R;225
B) U-R-T-S-V;175
C) R-S-T-U-V;240
D) U-S-V-T-R;200
E) V-U-T-S-R;250
Correct Answer:
Verified
Q67: Average completion time for a schedule sequence
Q69: Which of the following is an advantage
Q76: Five jobs are waiting to be processed.Their
Q76: Which critical ratio value implies that a
Q78: Five welding jobs are waiting to be
Q78: Flow time represents the time
A) an order
Q87: Which of the following is true regarding
Q87: _ means frequent, high-quality, small lot sizes
Q89: _ is the assignment of jobs to
Q93: Because facility capacity, set-up time, and run
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents