A manager must decide on the mix of products to produce for the coming week.Product A requires three minutes per unit for molding,two minutes per unit for painting,and one minute for packing.Product B requires two minutes per unit for molding,four minutes for painting,and three minutes per unit for packing.There will be 600 minutes available for molding,600 minutes for painting,and 420 minutes for packing.Both products have contributions of $1.50 per unit.Answer the following questions;base your work on the solution panel provided.
a.What combination of A and B will maximize contribution?
b.What is the maximum possible contribution?
c.Are any resources not fully used up? Explain.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q47: The _ is the set of all
Q61: A financial advisor is about to build
Q63: The Queen City Nursery manufactures bags of
Q63: A difference between minimization and maximization problems
Q64: A craftsman builds two kinds of birdhouses,one
Q67: In sensitivity analysis,a zero shadow price (or
Q70: Rienzi Farms grows sugar cane and soybeans
Q72: A shadow price (or dual value) reflects
Q75: _ is an analysis that projects how
Q76: What is sensitivity analysis?
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents