Riker Co.is considering which of 4 different projects to undertake in order to maximize its net present value (NPV) .Define Xi as a binary variable that equals 1 if project i is undertaken and 0 otherwise,for i = 1,2,3,4.The NPV and required capital (in millions) for each project are listed below. Which of the following represents the constraint(s) stating that project 1 must be undertaken and at least one of the other projects must be undertaken?
A) X1 + X2 ≤ 1,and X1 + X3 ≤ 1,and X1 + X4 ≤ 1
B) X1 ≥1,and X2 + X3 + X4 ≥ 1
C) X1 + X2 ≥ 1,and X1 + X3 ≥ 1,and X1 + X4 ≥ 1
D) X1 ≥1,and X2 + X3 + X4 ≤ 3
E) X1 + X2 + X3 + X4 ≥ 2
Correct Answer:
Verified
Q81: A stereo mail order center has 8,000
Q83: The property manager of a city government
Q84: What is the simplex method?
Q87: Constraints are needed to solve linear programming
Q88: If we wish to ensure that decision
Q89: Tom is a habitual shopper at garage
Q90: Capital Co.is considering 5 different projects.Define Xi
Q96: Binary variables can only take on the
Q101: _ variables allow us to introduce "yes-or-no"
Q102: Describe how to incorporate fixed costs into
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents