A local project being analyzed by PERT has 42 activities,13 of which are on the critical path.If the estimated time along the critical path is 105 days with a project variance of 25,what is the probability that the project will be completed in 95 days or less?
A) -0.4
B) 0.0228
C) 0.3444
D) 0.9772
E) 4.2
Correct Answer:
Verified
Q90: In a PERT network, non-critical activities that
Q96: Which of the following statements regarding PERT
Q97: Contract requirements state that a project must
Q99: The beta distribution is used in project
Q101: A project whose critical path has an
Q101: Consider the network described in the table
Q103: Project management at the Tour de France
Q105: A partially solved PERT problem is detailed
Q125: A network has been crashed to the
Q129: _ is decreasing activity time in a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents