Which of these statements regarding time-cost tradeoffs in CPM networks is true?
A) Crashing is not possible unless there are multiple critical paths.
B) Crashing a project often reduces the length of long-duration,but noncritical,activities.
C) Activities not on the critical path can never be on the critical path,even after crashing.
D) Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
E) The crash time always exceeds the normal time.
Correct Answer:
Verified
Q105: A partially solved PERT problem is detailed
Q107: How is the expected completion time of
Q107: A network consists of the following list.Times
Q111: Three critical path activities are candidates for
Q112: In project management, crashing an activity must
Q112: Two critical path activities are candidates for
Q113: Pirmin's Bike Shop is behind on a
Q114: Describe in words how to calculate a
Q115: Two critical path activities are candidates for
Q120: Shortening the project's duration by deleting unnecessary
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents