Which of the following statements regarding time-cost tradeoffs in CPM networks is false?
A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.
Correct Answer:
Verified
Q109: A project manager is interested in crashing
Q111: Three critical path activities are candidates for
Q112: Two critical path activities are candidates for
Q113: Pirmin's Bike Shop is behind on a
Q114: Describe in words how to calculate a
Q115: Two critical path activities are candidates for
Q117: If an activity whose normal duration is
Q119: Three critical path activities are candidates for
Q120: If an activity whose normal duration is
Q121: Which of the following is NOT performed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents