Table J.2 Suppose That the Following Six Jobs Must Be Scheduled Through

Question 36

Multiple Choice

Table J.2
Suppose that the following six jobs must be scheduled through a car repair facility:
Table J.2 Suppose that the following six jobs must be scheduled through a car repair facility:    -Use the information in Table J.2.What is the past due time of the last job completed if sequencing is done using the earliest due date rule? A) 30 B) 40 C) 45 D) 60
-Use the information in Table J.2.What is the past due time of the last job completed if sequencing is done using the earliest due date rule?


A) 30
B) 40
C) 45
D) 60