Table 7.11 the Pennsylvania Appliance Company Is Installing an Assembly Line to Line

Question 111

Multiple Choice

Table 7.11
The Pennsylvania Appliance Company is installing an assembly line to produce vacuum cleaners,and you,as an operations manager,are responsible for balancing the line.The work elements to be performed are listed,along with their times and immediate predecessors.
Table 7.11 The Pennsylvania Appliance Company is installing an assembly line to produce vacuum cleaners,and you,as an operations manager,are responsible for balancing the line.The work elements to be performed are listed,along with their times and immediate predecessors.    -Use the information in Table 7.11.The company is planning to operate 2 shifts per day 8 hours per shift.If the desired output rate of the line is 480 units per day,what is the highest efficiency possible for a balanced line? A) less than 91% B) more than 91% and less than 93% C) more than 93% and less than 95% D) more than 95%
-Use the information in Table 7.11.The company is planning to operate 2 shifts per day 8 hours per shift.If the desired output rate of the line is 480 units per day,what is the highest efficiency possible for a balanced line?


A) less than 91%
B) more than 91% and less than 93%
C) more than 93% and less than 95%
D) more than 95%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents