The following tasks are required to assemble an alarm clock radio. The assembly line would like to achieve an output of 40 finished radios per hour.
a. What takt time is required to achieve the desired rate of output?
b. What is the theoretical minimum number of workstations required to achieve the desired rate of output per hour?
c. Use the longest operating time (LOT) heuristic to assign tasks to workstations.
d. What is the efficiency of the line balance you determined in part c?
e. What is the balance delay of the line balance you determined in part c?
a. What takt time is required to achieve the desired rate of output?b. What is the theoretical minimum number of workstations required to achieve the desired rate of output per hour?
c. Use the longest operating time (LOT) heuristic to assign tasks to workstations.
d. What is the efficiency of the line balance you determined in part c?
e. What is the balance delay of the line balance you determined in part c?
التوضيح
Line balancing:
Line balancing is the p...
Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb
لماذا لم يعجبك هذا التمرين؟
أخرى 8 أحرف كحد أدنى و 255 حرفاً كحد أقصى
حرف 255