Shown below are the planning period's demand and the standard hours required for four products from a company's sales and operations plan. Assuming that the company has 65,000 hours of labor available during the planning period, determine whether the sales and operations plan is feasible. 

التوضيح
Rough-cut capacity planning:
It is the ...