Item A has a gross requirement for 1000 in week 5. There are currently 300 of the item on hand with a scheduled receipt of 100 items in week 2. The order quantity is lot for lot, and there is a two-week lead time. Complete the MRP record for item A.
التوضيح
Material requirement management (MRP):
...