Three time estimates for a task in a project are as follows:
Optimistic completion time = 4 weeks
Most likely completion time = 9 weeks
Pessimistic completion time = 15 weeks
Calculate the expected task completion time.
Optimistic completion time = 4 weeks
Most likely completion time = 9 weeks
Pessimistic completion time = 15 weeks
Calculate the expected task completion time.
التوضيح
Estimated task completion time:
Estimat...