Suppose that a task in a project has the following time estimates:
t 0 = optimistic completion time = 6 weeks
t m = most likely completion time = 8 weeks
t p - pessimistic completion time = 11 weeks
Compute the expected task completion time.
t 0 = optimistic completion time = 6 weeks
t m = most likely completion time = 8 weeks
t p - pessimistic completion time = 11 weeks
Compute the expected task completion time.
التوضيح
Estimated task completion time:
Estimat...