Suppose that a task in a project has the following time estimates:
t 0 = optimistic completion time = 6 weeks
t m = most likely completion time - 8 weeks
t p = pessimistic completion time = 11 weeks
Compute the expected task variance.
t 0 = optimistic completion time = 6 weeks
t m = most likely completion time - 8 weeks
t p = pessimistic completion time = 11 weeks
Compute the expected task variance.
التوضيح
Task variance:
Task variance is helps t...