expand icon
book Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb cover

Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb

النسخة 1الرقم المعياري الدولي: 9780134110219
book Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb cover

Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb

النسخة 1الرقم المعياري الدولي: 9780134110219
تمرين 3
A project has a task with the following task time estimates:
Pessimistic completion time = 18 weeks
Most likely completion time = 15 weeks
Optimistic completion time = 7 weeks.
What is the variance for the task?
التوضيح
موثّق
like image
like image

Task variance:
Task variance is helps t...

close menu
Managing Supply Chain and Operations 1st Edition by Thomas Foster ,Scott Sampson,Cynthia Wallin,Scott Webb
cross icon