تمرين 1
The general manager for Woodslome Appliance Company Plant #A14 in Mexico City has four independent projects that she can fund this year to improve surface durability on stainless steel products. The project costs and 18% per year PW values are as shown. What projects should be accepted if the budget limit is
a) no limit and b) $55,000 The general manager for Woodslome Appliance Company Plant #A14 in Mexico City has four independent projects that she can fund this year to improve surface durability on stainless steel products. The project costs and 18% per year PW values are as shown. What projects should be accepted if the budget limit is  a) no limit and b) $55,000
التوضيح
موثّق
like image
like image

12.9 (a) Select projects 2, 3 ...